The orderer, in the case set forth in Article 31, paragraph (1) of the Act, when having persons engaged in work pertaining to the contractor use tunnels, etc., and when those persons engaged in work carry out the construction work of tunnels, etc. (limited to cases where there is a risk of endangering persons engaged in work due to cave-ins or falling of rocks), must take measures to prevent cave-ins or falling of rocks, such as providing tunnel shoring and installing rock bolts in the tunnels, etc.
As regards the tunnel shoring set forth in the preceding paragraph, the orderer must ensure that the shoring complies with the standards of the tunnel shoring prescribed in Part II, Chapter VI, Section 2, Subsection 2 (limited to Article 390, Article 391, and Article 394).
定義第二十四条の六第一項
ずい道及びたて坑以外の坑(採石法(昭和二十五年法律第二百九十一号)第二条に規定する岩石の採取のためのものを除く。)
わかりやすく言うと
ずい道と、たて坑以外の坑をまとめた呼び名です。ただし、採石法で定める花こう岩などの岩石を採取するための坑は含みません。
略称規定第六百四十四条第一項
法第三十一条第一項の注文者(以下「注文者」という。)は、同項の場合において、請負人(同項の請負人をいう。以下この章において同じ。)に係る作業従事者にくい打機又はくい抜機を使用させるときは、当該くい打機又はくい抜機については…
わかりやすく言うと
建設業その他政令で定める業種の事業の仕事を、自らも行う注文者のことです(労働安全衛生法第三十一条第一項)。
定義第六百四十四条第一項・この章の中だけ
同項の請負人
わかりやすく言うと
建設業などの特定事業の仕事を自ら行う注文者の請負人のことで、仕事が何段階もの請負で行われるときは、その後に続く全ての請負契約の請負人を含みます(労働安全衛生法第三十一条第一項)。