Article 651Measures Concerning Tunnels

第六百五十一条(ずい道等についての措置)

The orderer, in the case set forth in Article 31, paragraph (1) of the Act, when having persons engaged in work pertaining to the contractor use tunnels, etc., and when those persons engaged in work carry out the construction work of tunnels, etc. (limited to cases where there is a risk of endangering persons engaged in work due to cave-ins or falling of rocks), must take measures to prevent cave-ins or falling of rocks, such as providing tunnel shoring and installing rock bolts in the tunnels, etc.

注文者は、法第三十一条第一項の場合において、請負人に係る作業従事者にずい道等を使用させる場合で、当該作業従事者がずい道等の建設の作業を行うとき(落盤又は肌落ちにより作業従事者に危険を及ぼすおそれのあるときに限る。)は、当該ずい道等についてずい道支保工を設け、ロツクボルトを施す等落盤又は肌落ちを防止するための措置を講じなければならない。

As regards the tunnel shoring set forth in the preceding paragraph, the orderer must ensure that the shoring complies with the standards of the tunnel shoring prescribed in Part II, Chapter VI, Section 2, Subsection 2 (limited to Article 390, Article 391, and Article 394).

注文者は、前項のずい道支保工については、第二編第六章第二節第二款(第三百九十条、第三百九十一条及び第三百九十四条に限る。)に規定するずい道支保工の基準に適合するものとしなければならない。