When carrying out simplified forestry cableway work, the employer must establish in advance a work plan suited to what has become known through the investigation under the provisions of the preceding Article, and carry out the work in accordance with that work plan.
The work plan set forth in the preceding paragraph must indicate the following matters:
前項の作業計画は、次の事項が示されているものでなければならない。
places where supports and the main equipment is installed;
支柱及び主要機器の配置の場所
type and diameter of wire ropes to be used;
使用するワイヤロープの種類及びその直径
the maximum working load;
最大使用荷重
type and maximum traction force of the yarder of the simplified skyline logging cable crane;
簡易架線集材装置の集材機の種類及び最大けん引力
method of simplified forestry cableway work; and
簡易林業架線作業の方法
emergency measures to be taken in the event of an industrial injury and method of transporting injured or ill persons.
労働災害が発生した場合の応急の措置及び傷病者の搬送の方法
When having formulated the work plan set forth in paragraph (1), the employer must inform the workers concerned of the matters set forth in items (i) through (iii), (v) and (vi) of the preceding paragraph.
事業者は、第一項の作業計画を定めたときは、前項第一号から第三号まで、第五号及び第六号の事項について関係労働者に周知させなければならない。
定義第三十六条第一項第七号の二
集材機、架線、搬器、支柱及びこれらに附属する物により構成され、動力を用いて、原木等を巻き上げ、かつ、原木等の一部が地面に接した状態で運搬する設備