When having installed tunnel shoring, the employer must inspect the following matters each day and after a moderate or greater earthquake, and immediately reinforce or repair the shoring when having found any abnormality:
事業者は、ずい道支保工を設けたときは、毎日及び中震以上の地震の後、次の事項について点検し、異常を認めたときは、直ちに補強し、又は補修しなければならない。
existence and condition of damage, deformation, corrosion, displacements and coming off of the components;
部材の損傷、変形、腐食、変位及び脱落の有無及び状態
degree of compression of the components;
部材の緊圧の度合
condition of the connecting parts and crossing parts of the components; and
部材の接続部及び交さ部の状態
existence and condition of subsidence of the leg parts.
脚部の沈下の有無及び状態