When having installed shoring, the employer must inspect the following matters once every period not exceeding seven days, after a moderate or greater earthquake, and after the occurrence of a situation that has a risk of rapidly weakening the ground due to heavy rain, etc., and immediately reinforce or make repairs when having found any abnormality:
事業者は、土止め支保工を設けたときは、その後七日をこえない期間ごと、中震以上の地震の後及び大雨等により地山が急激に軟弱化するおそれのある事態が生じた後に、次の事項について点検し、異常を認めたときは、直ちに、補強し、又は補修しなければならない。
existence and condition of damage, deformation, corrosion, displacement and coming off of components;
部材の損傷、変形、腐食、変位及び脱落の有無及び状態
degree of compression of struts; and
切りばりの緊圧の度合
condition of the connecting parts, mounting parts and crossing parts of components.
部材の接続部、取付け部及び交さ部の状態