Article 517-16Signal for Pulling Down Work

第五百十七条の十六(引倒し等の作業の合図)

When carrying out the work of pulling down outer walls, posts, etc., in carrying out the work set forth in Article 6, item (xv)-5 of the Order, the employer must set fixed signals for the pulling down work, and make them known to the workers concerned.

事業者は、令第六条第十五号の五の作業を行う場合において、外壁、柱等の引倒し等の作業を行うときは、引倒し等について一定の合図を定め、関係労働者に周知させなければならない。

In carrying out the work of pulling down, etc. set forth in the preceding paragraph, when there is a risk of danger arising from the pulling down, etc. to persons engaged in work other than the workers engaged in that work of pulling down, etc. (hereinafter referred to as "other persons engaged in work" in this Article), the employer must have the workers engaged in that work give the signals set forth in the same paragraph in advance, and must not have that work of pulling down, etc. carried out unless the workers have confirmed that the other persons engaged in work have evacuated.

事業者は、前項の引倒し等の作業を行う場合において、当該引倒し等の作業に従事する労働者以外の作業従事者(以下この条において「他の作業従事者」という。)に引倒し等により危険を生ずるおそれのあるときは、当該引倒し等の作業に従事する労働者に、あらかじめ、同項の合図を行わせ、他の作業従事者が避難したことを確認させた後でなければ、当該引倒し等の作業を行わせてはならない。

The worker engaging in the work of pulling down, etc. set forth in paragraph (1), when there is a risk of the danger set forth in the preceding paragraph, must give signals in advance, and must not carry out that work of pulling down, etc. unless having confirmed that other persons engaged in work have evacuated.

第一項の引倒し等の作業に従事する労働者は、前項の危険を生ずるおそれのあるときは、あらかじめ、合図を行い、他の作業従事者が避難したことを確認した後でなければ、当該引倒し等の作業を行つてはならない。