When carrying out forestry cableway work (excluding the work set forth in Article 6, item (iii) of the Order), the employer must designate a work director for the work and have that person direct the work based on the work plan set forth in Article 151-125, paragraph (1).
事業者は、林業架線作業(令第六条第三号の作業を除く。)を行うときは、当該作業の指揮者を定め、その者に第百五十一条の百二十五第一項の作業計画に基づき作業の指揮を行わせなければならない。
Read this with the articles around it
forestry cableway workmachine translation
「林業架線作業」
Assembling, dismantling, changing or repairing a cable yarding system (機械集材装置) or a timber cableway (運材索道), or gathering or carrying timber with them.
Defined inArticle 151-124, paragraph (1)