Article 653Measures Concerning a Hoistway

第六百五十三条(物品揚卸口等についての措置)

In the case set forth in Article 31, paragraph (1) of the Act, when the orderer has persons engaged in work pertaining to the contractor use work floors, hoistways, pits, shafts or hatches of vessels, the orderer must install enclosures, handrails, covers, etc., at places where the height of these construction, equipment, or raw material is 2 m or more and there is a risk of endangering persons engaged in work due to falling; provided, however, that this does not apply when it is difficult to install enclosures, handrails, covers, etc., due to the nature of the work.

注文者は、法第三十一条第一項の場合において、請負人に係る作業従事者に、作業床、物品揚卸口、ピツト、坑又は船舶のハツチを使用させるときは、これらの建設物等の高さが二メートル以上の箇所で墜落により作業従事者に危険を及ぼすおそれのあるところに囲い、手すり、覆い等を設けなければならない。ただし、囲い、手すり、覆い等を設けることが作業の性質上困難なときは、この限りでない。

In the case referred to in the preceding paragraph, for a work floor located at a place exceeding 1.5 m in height or in depth, the orderer must install facilities, etc., for persons engaged in work to ascend and descend safely.

注文者は、前項の場合において、作業床で高さ又は深さが一・五メートルを超える箇所にあるものについては、作業従事者が安全に昇降するための設備等を設けなければならない。