Article 85Machinery or Other Such Equipment Subject to Notification of the Plan

第八十五条(計画の届出をすべき機械等)

The machinery or other such equipment specified by Order of the Ministry of Health, Labour and Welfare under Article 88, paragraph (1) of the Act is to be, beyond what is prescribed in other Ministerial Orders based on the Act, the machinery or other such equipment listed in the left column of Appended Table 7; provided, however, that this excludes machinery or other such equipment listed in the left column of Appended Table 7 that falls under any of the following items:

法第八十八条第一項の厚生労働省令で定める機械等は、法に基づく他の省令に定めるもののほか、別表第七の上欄に掲げる機械等とする。ただし、別表第七の上欄に掲げる機械等で次の各号のいずれかに該当するものを除く。

machinery or other such equipment (excluding specified machinery or other such equipment under Article 37, paragraph (1) of the Act and concrete form shoring set forth in Article 6, item (xiv) of the Order (hereinafter referred to as "concrete form shoring")) other than skyline logging cable cranes, timber cableways (meaning equipment consisting of cables, carriers, supporting poles and things attached to them, which carries logs or fuelwood through the air over a fixed section; the same applies hereinafter), temporary passages and scaffolds, that is to be removed within a period of less than six months;

機械集材装置、運材索道(架線、搬器、支柱及びこれらに附属する物により構成され、原木又は薪炭材を一定の区間空中において運搬する設備をいう。以下同じ。)、架設通路及び足場以外の機械等(法第三十七条第一項の特定機械等及び令第六条第十四号の型枠支保工(以下「型枠支保工」という。)を除く。)で、六月未満の期間で廃止するもの

skyline logging cable cranes, timber cableways, temporary passages or scaffolds for which the period from assembly to dismantling is less than 60 days.

機械集材装置、運材索道、架設通路又は足場で、組立てから解体までの期間が六十日未満のもの