Article 402Alteration in Quarrying Work Plan

第四百二条(採石作業計画の変更)

In carrying out the quarrying work, when the quarrying work plan prescribed in Article 400, paragraph (1) has become unsuitable to the condition of the natural ground which became known by the inspection pursuant to the provisions of the preceding Article, etc., the employer must change the quarrying work plan so that it suits the condition of the ground without delay, and carry out the quarrying work according to the changed quarrying work plan.

事業者は、採石作業を行なう場合において、第四百条第一項の採石作業計画が前条の規定による点検等により知り得た地山の状態に適応しなくなつたときは、遅滞なく、当該採石作業計画を当該地山の状態に適応するよう変更し、かつ、変更した採石作業計画によつて作業を行なわなければならない。