Article 575-12Measures to be Taken When It Rains

第五百七十五条の十二(降雨時の措置)

In carrying out construction work on a river with a danger of debris flow where there is a risk of a debris flow due to rainfall, the employer must take measures to become aware of the occurrence of a debris flow at an early stage, such as placing a watcher; provided, however, that this does not apply when the work has been promptly suspended and persons engaged in work have been evacuated to a safe place.

事業者は、土石流危険河川において建設工事の作業を行う場合において、降雨があつたことにより土石流が発生するおそれのあるときは、監視人の配置等土石流の発生を早期に把握するための措置を講じなければならない。ただし、速やかに作業を中止し、作業従事者を安全な場所に退避させたときは、この限りでない。