Article 400Quarrying Work Plan

第四百条(採石作業計画)

When carrying out the quarrying work, the employer must formulate in advance a quarrying work plan that conform with what became known by the investigation pursuant to the provisions of the preceding Article, and carry out the work according to the work plan.

事業者は、採石作業を行なうときは、あらかじめ、前条の規定による調査により知り得たところに適応する採石作業計画を定め、かつ、当該採石作業計画により作業を行なわなければならない。

The quarrying work plan set forth in the preceding paragraph must indicate the following matters:

前項の採石作業計画は、次の事項が示されているものでなければならない。

in making a distinction between open casting or underground casting and for open casting, the distinction among the step quarrying system, slope quarrying system or glory hole system;

露天掘り又は坑内掘りの別及び露天掘りにあつては、階段採掘法、傾斜面掘削法又はグローリホール法の別

the height and gradient of the excavation surface;

掘削面の高さ及びこう配

the position and depth of the steps of the excavation surface;

掘削面の段の位置及び奥行き

the method of preventing cave-in, falling of rocks, and collapse of sidewalls in the pit;

坑内における落盤、肌落ち及び側壁の崩壊防止の方法

the method of blasting;

発破の方法

the method of breaking rocks into small pieces;

岩石の小割の方法

the place for processing rocks;

岩石の加工の場所

the method of loading, transporting earth and sand or rocks and the route of transportation;

土砂又は岩石の積込み及び運搬の方法並びに運搬の経路

the type and capability of excavating machines, machines for breaking rocks into small pieces, loading machines or transporting machines to be used; and

使用する掘削機械、小割機械、積込機械又は運搬機械の種類及び能力

the method of disposing surface earth or spring water.

表土又は湧水の処理の方法