In carrying out excavating work of tunnels, etc., when the construction plan set forth in Article 380, paragraph (1) becomes unsuitable to the conditions of natural ground which became known by the observation pursuant to the provisions of Article 381, paragraph (1), the inspection pursuant to the provisions of Article 382, the measurement pursuant to the provisions of Article 382-2, etc., the employer must change the construction plan without delay so that suits the conditions of the natural ground, and carry out the excavating work according to the changed construction plan.
事業者は、ずい道等の掘削の作業を行う場合において、第三百八十条第一項の施工計画が第三百八十一条第一項の規定による観察、第三百八十二条の規定による点検、第三百八十二条の二の規定による測定等により知り得た地山の状態に適応しなくなつたときは、遅滞なく、当該施工計画を当該地山の状態に適応するよう変更し、かつ、変更した施工計画によつて作業を行わなければならない。
Read this with the articles around it
tunnel, etc.machine translation
「ずい道等」
A tunnel, or an underground pit other than a vertical shaft, leaving out pits dug to extract rock as described in Article 2 of the Quarrying Act.
Defined inArticle 24-6, paragraph (1)