Article 188Measures to Be Taken When Hoisting Sheet Piles and Rods

第百八十八条(矢板、ロッド等のつり上げ時の措置)

When hoisting piles, sheet piles and rods, etc., with a pile driver or a boring machine, the employer must have the operator of the machine hoist piles in a manner that the hook part is located right under the sheave or the pulley block of the machine. The same applies to the case of hoisting a pile or sheet pile by providing a pile driver with a hoisting device such as a gin pole.

事業者は、くい打機又はボーリングマシンで、くい、矢板、ロッド等をつり上げるときは、その玉掛部が巻上げ用みぞ車又は滑車装置の直下になるようにつり上げさせなければならない。くい打機にジンポール等の物上げ装置を取り付けて、くい、矢板等をつり上げる場合においても、同様とする。