With regard to a wire rope used for the winch or slings of a cable yarding machine, the employer must not use one that falls under any of the following items:
事業者は、架線集材機械のウインチ又はスリングに用いるワイヤロープについては、次のいずれかに該当するものを使用してはならない。
Search provisions, jump to a law or an article
This text is not in force yetIt on 1 April 2027, in 4 months
Read the text in force →労働安全衛生規則
Chapter I-3 Logging Machines, etc. (Articles 151-121 to 151-138)
The law as Ministerial Order Partially Amending the Ordinance on Industrial Safety and Health (Ministry of Health, Labour and Welfare Order No. 112 of 2026) leaves it, with the words it changes marked.
The main text is read a page at a time: a chapter to a page, and a long chapter in runs of articles. The whole main text, and the supplementary provisions and appended tables this amendment changes. Those it leaves untouched are on the page for the text in force.
With regard to a wire rope used for the winch or slings of a cable yarding machine, the employer must not use one that falls under any of the following items:
事業者は、架線集材機械のウインチ又はスリングに用いるワイヤロープについては、次のいずれかに該当するものを使用してはならない。
those in which 10% or more of the element wires (excluding filler wires; the same applies hereinafter in this item) have broken within one lay of the wire rope;
ワイヤロープ一よりの間において素線(フイラ線を除く。以下本号において同じ。)数の十パーセント以上の素線が切断したもの
those with the reduction ratio of a diameter due to wear-out that exceeds 7% of the nominal diameter;
摩耗による直径の減少が公称径の七パーセントを超えるもの
those with kinks; and
キンクしたもの
those with marked deformation or corrosion.
著しい形崩れ又は腐食のあるもの
When carrying out work using a cable yarding machine, the employer must, before starting the work of the day, check the condition of the slings used for the work, and if an abnormality is found, must immediately repair or replace them.
事業者は、架線集材機械を用いて作業を行うときは、その日の作業を開始する前に、当該作業に用いるスリングの状態について点検し、異常を認めたときは、直ちに、補修し、又は取り替えなければならない。
With regard to the operation of the winch of a cable yarding machine, the employer must determine fixed signals and the person who gives the signals, and have those signals used in the operation.
事業者は、架線集材機械のウインチの運転について、一定の合図及び合図を行う者を定め、運転に当たつては、当該合図を使用させなければならない。
The operator of the winch of the cable yarding machine set forth in the preceding paragraph must follow the signals set forth in that paragraph.
前項の架線集材機械のウインチの運転者は、同項の合図に従わなければならない。
When carrying out forestry cableway work (meaning work of assembling, dismantling, altering or repairing a skyline logging cable crane or timber cableway, or work of yarding or transporting timber using such equipment; the same applies hereinafter), the employer must, in order to prevent danger to workers due to a yarder or timber hauling machine falling, collapse of the natural ground, collapse of a support, etc., investigate in advance the area, topography, ground condition, etc. of the place where the work is to be carried out, the condition of the standing trees to be used as supports, and the shape, etc. of the logs, etc. to be transported, and record the results.
事業者は、林業架線作業(機械集材装置若しくは運材索道の組立て、解体、変更若しくは修理の作業又はこれらの設備による集材若しくは運材の作業をいう。以下同じ。)を行うときは、集材機又は運材機の転落、地山の崩壊、支柱の倒壊等による労働者の危険を防止するため、あらかじめ、当該作業に係る場所について広さ、地形、地盤の状態等、支柱とする立木の状態及び運搬する原木等の形状等を調査し、その結果を記録しておかなければならない。
When carrying out forestry cableway work, the employer must establish in advance a work plan suited to what has become known through the investigation under the provisions of the preceding Article, and carry out the work in accordance with that work plan.
事業者は、林業架線作業を行うときは、あらかじめ、前条の規定による調査により知り得たところに適応する作業計画を定め、かつ、当該作業計画により作業を行わなければならない。
The work plan set forth in the preceding paragraph must indicate the following matters:
前項の作業計画は、次の事項が示されているものでなければならない。
places where supports and the main equipment is installed;
支柱及び主要機器の配置の場所
type and diameter of wire ropes to be used;
使用するワイヤロープの種類及びその直径
central dangling ratio;
中央垂下比
maximum working load, distance between carriers, and maximum loading capacity of each carrier;
最大使用荷重、搬器と搬器の間隔及び搬器ごとの最大積載荷重
type and maximum traction force of the yarder of the skyline logging cable crane;
機械集材装置の集材機の種類及び最大けん引力
method of forestry cableway work; and
林業架線作業の方法
emergency measures to be taken in the event of an industrial injury and method of transporting injured or ill persons.
労働災害が発生した場合の応急の措置及び傷病者の搬送の方法
When having formulated the work plan set forth in paragraph (1), the employer must inform the workers concerned of the matters set forth in items (i), (ii), (iv), (vi) and (vii) of the preceding paragraph.
事業者は、第一項の作業計画を定めたときは、前項第一号、第二号、第四号、第六号及び第七号の事項について関係労働者に周知させなければならない。
As regards the work set forth in Article 6, item (iii) of the Order, the employer must appoint an operations supervisor of forestry cableway from the persons who have obtained the license for operations supervisor of forestry cableway.
事業者は、令第六条第三号の作業については、林業架線作業主任者免許を受けた者のうちから、林業架線作業主任者を選任しなければならない。
The employer must have the operations supervisor of forestry cableways carry out the following matters:
事業者は、林業架線作業主任者に、次の事項を行わせなければならない。
to decide the work method and arrangement of workers, and directly supervise the work;
作業の方法及び労働者の配置を決定し、作業を直接指揮すること。
to check for defects in materials and function of instruments and tools, and remove those defective; and
材料の欠点の有無並びに器具及び工具の機能を点検し、不良品を取り除くこと。
to monitor the use of fall arrest equipment with the required performance, etc. and safety helmets during the work.
作業中、要求性能墜落制止用器具等及び保護帽の使用状況を監視すること。
When carrying out forestry cableway work (excluding the work set forth in Article 6, item (iii) of the Order), the employer must designate a work director for the work and have that person direct the work based on the work plan set forth in Article 151-125, paragraph (1).
事業者は、林業架線作業(令第六条第三号の作業を除く。)を行うときは、当該作業の指揮者を定め、その者に第百五十一条の百二十五第一項の作業計画に基づき作業の指揮を行わせなければならない。
As regards a skyline logging cable crane or a timber cableway, the employer must conform to the requirements of the following items:
事業者は、機械集材装置又は運材索道については、次に定めるところによらなければならない。
to provide an effective braking device for stopping carriers or lifted cargos as necessary except when there is no need to brake the carriers or stop the lifted cargos;
搬器又はつり荷を制動させる必要がない場合を除き、搬器又はつり荷を適時停止させることができる有効な制動装置を備えること。
to wind the main cable, stay ropes and work ropes to be attached to stationary objects twice or more onto solid stationary objects such as supports, standing trees, stumps, etc., and fasten the ropes securely using clips, clamps or other fastening tools;
主索、控索及び固定物に取り付ける作業索は、支柱、立木、根株等の固定物で堅固なものに二回以上巻き付け、かつ、クリツプ、クランプ等の緊結具を用いて確実に取り付けること。
to use two stays or more to stabilize the top of the supports, and make the angle formed by a stay and a support 30 degrees or more;
支柱の頂部を安定させるための控えは、二以上とし、控えと支柱とのなす角度を三十度以上とすること。
to securely fasten saddle blocks, guide blocks, etc., using shackles, anchor ropes or other fittings that do not have a risk of breaking or coming off by the load applied to the mounting part;
サドルブロツク、ガイドブロツク等は、取付け部が受ける荷重により破壊し、又は脱落するおそれのないシヤツクル、台付け索等の取付け具を用いて確実に取り付けること。
to use carriers, main cable supporting devices and other accessories that have sufficient strength; and
搬器、主索支持器その他の附属器具は、十分な強度を有するものを使用すること。
when fastening the end of the towing ropes or work ropes to a carrier or a loading block, to securely fasten with clips, eye splices or other methods.
えい索又は作業索の端部を搬器又はロージングブロツクに取り付けるときは、クリツプ止め、アイスプライス等の方法により確実に取り付けること。
As regards the ropes for skyline logging cable cranes or timber cableways listed in the left column of the following Table, the employer must use wire ropes that have a safety coefficient equivalent to or more than that listed in the right column of the same Table in accordance with the use of the cables:
| Intended Use of Wire Rope | Safety Coefficient |
| Main cable | 2.7 |
| Towing rope | 4.0 |
| Work rope (excluding hoisting rope) | 4.0 |
| Hoisting rope | 6.0 |
| Stay rope | 4.0 |
| Anchor rope | 4.0 |
| Cargo lifting rope | 6.0 |
事業者は、機械集材装置又は運材索道の次の表の上欄に掲げる索については、その用途に応じて、安全係数が同表の下欄に掲げる値以上であるワイヤロープを使用しなければならない。
| ワイヤロープの用途 | 安全係数 |
| 主索 | 二・七 |
| えい索 | 四・〇 |
| 作業索(巻上げ索を除く。) | 四・〇 |
| 巻上げ索 | 六・〇 |
| 控索 | 四・〇 |
| 台付け索 | 四・〇 |
| 荷吊り索 | 六・〇 |
The safety coefficient set forth in the preceding paragraph must be the value obtained by dividing the value of the breaking load of wire ropes by the value of maximum tension in accordance with the constructing condition of the skyline logging cable cranes or timber cableways and the load applied to the wire ropes.
前項の安全係数は、ワイヤロープの切断荷重の値を、当該機械集材装置又は運材索道の組立ての状態及び当該ワイヤロープにかかる荷重に応じた最大張力の値で除した値とする。
As regards a wire rope for a skyline logging cable crane or a timber cableway, the employer must not use a wire rope falling under any of the following items:
事業者は、機械集材装置又は運材索道のワイヤロープについては、次のいずれかに該当するものを使用してはならない。
those in which 10% or more of the element wires (excluding filler wires; the same applies hereinafter in this item) have broken within one lay of the wire rope;
ワイヤロープ一よりの間において素線(フイラ線を除く。以下本号において同じ。)数の十パーセント以上の素線が切断したもの
those with the reduction ratio of a diameter due to wear-out that exceeds 7% of the nominal diameter;
摩耗による直径の減少が公称径の七パーセントを超えるもの
those with kinks; and
キンクしたもの
those with marked deformation or corrosion.
著しい形崩れ又は腐食のあるもの
As regards the work ropes for skyline logging cable cranes (excluding endless cables), the employer must take the following measures:
事業者は、機械集材装置の作業索(エンドレスのものを除く。)については、次に定める措置を講じなければならない。
the length of work ropes must be a length that enables to leave two or more windings around the drum of the yarder when the ropes are used at the maximum length; and
作業索は、これを最大に使用した場合において、集材機の巻胴に二巻以上を残すことができる長さとすること。
the end of work ropes is to be securely fastened to the drum of the yarder with clamps, clips or other fastening tools.
作業索の端部は、集材機の巻胴にクランプ、クリツプ等の緊結具を用いて確実に取り付けること。
With regard to a skyline logging cable crane, the employer must take measures to prevent danger to workers due to over-winding of the hoisting rope, such as providing an over-winding prevention device.
事業者は、機械集材装置については、巻過防止装置を備える等巻上げ索の巻過ぎによる労働者の危険を防止するための措置を講じなければならない。
With regard to the yarder of a skyline logging cable crane or the timber hauling machine of a timber cableway, the employer must take the following measures; provided, however, that this does not apply where a cable yarding machine is used as the yarder of a skyline logging cable crane.
事業者は、機械集材装置の集材機又は運材索道の運材機については、次に定める措置を講じなければならない。ただし、架線集材機械を機械集材装置の集材機として用いる場合は、この限りでない。
to install the yarder or timber hauling machine so that it does not float up, slip out of place or swing; and
浮き上がり、ずれ又は振れが生じないように据え付けること。
to provide a ratchet or brakes fitted with studs.
歯止装置又は止め金つきブレーキを備え付けること。
When using a cable yarding machine as the yarder of a skyline logging cable crane, the employer must take the following measures:
事業者は、架線集材機械を機械集材装置の集材機として用いる場合は、次に定める措置を講じなければならない。
to take measures to prevent the cable yarding machine from breaking into a run, such as securely applying the brake for keeping the cable yarding machine in a stopped state; and
架線集材機械の停止の状態を保持するためのブレーキを確実にかける等の架線集材機械の逸走を防止する措置を講ずること。
to take measures to prevent danger to workers due to overturning or falling of the cable yarding machine, such as extending the outriggers over steel plates, etc. having the necessary width and strength, or lowering the blade to the ground.
アウトリガーを必要な広さ及び強度を有する鉄板等の上で張り出し、又はブレードを地上に下ろす等の架線集材機械の転倒又は転落による労働者の危険を防止するための措置を講ずること。
When using a cable yarding machine as the yarder of a skyline logging cable crane, the employer must endeavor not to use, at a road shoulder, inclined place, etc. where there is a risk of danger to workers due to overturning or falling of the cable yarding machine, a cable yarding machine other than one that has a roll-over protective structure and is equipped with a seat belt, and must endeavor to have the operator use the seat belt.
事業者は、架線集材機械を機械集材装置の集材機として用いる場合は、路肩、傾斜地等であつて、架線集材機械の転倒又は転落により労働者に危険が生ずるおそれのある場所においては、転倒時保護構造を有し、かつ、シートベルトを備えたもの以外の架線集材機械を使用しないよう努めるとともに、運転者にシートベルトを使用させるように努めなければならない。
With regard to the yarder of a skyline logging cable crane, the employer must not use one unless it is equipped with a solid head guard; provided, however, that this does not apply where there is no risk of danger to the operator due to falling of logs, etc.
事業者は、機械集材装置の集材機については、堅固なヘツドガードを備えたものでなければ使用してはならない。ただし、原木等の落下により運転者に危険を及ぼすおそれのないときは、この限りでない。
With regard to the yarder of a skyline logging cable crane, where there is a risk of danger to the operator due to logs, etc. coming flying, etc., the employer must not use one unless it is equipped with facilities for preventing that danger, such as a protective railing at the operator's seat.
事業者は、機械集材装置の集材機については、原木等の飛来等により運転者に危険を及ぼすおそれのあるときは、運転者席の防護柵等当該危険を防止するための設備を備えたものでなければ使用してはならない。
As regards skyline logging cable cranes, the employer must indicate their maximum working load at a readily visible location.
事業者は、機械集材装置については、最大使用荷重を見やすい箇所に表示しなければならない。
As regards skyline logging cable cranes, the employer must not use the cranes by applying a load exceeding the maximum working load set forth in the preceding paragraph.
事業者は、機械集材装置については、前項の最大使用荷重を超える荷重をかけて使用してはならない。