Ordinance on Industrial Safety and Health

労働安全衛生規則(ろうどうあんぜんえいせいきそく)

Chapter VI Prevention of Dangers in Excavating Work (Articles 355 to 375)

The law as Ministerial Order Partially Amending the Ordinance on Industrial Safety and Health, etc. (Ministry of Health, Labour and Welfare Order No. 89 of 2026) leaves it, with the words it changes marked.

The main text is read a page at a time: a chapter to a page, and a long chapter in runs of articles. The whole main text, and the supplementary provisions and appended tables this amendment changes. Those it leaves untouched are on the page for the text in force.

How the changes are shown

Underlined: words the amendment adds. A bar: where it removes words.Underlined: words the amendment adds. Struck through: the words it removes.Underlined: words the amendment adds. Struck through: the words it removes.

Chapter VI Prevention of Dangers in Excavating Work第六章 掘削作業等における危険の防止

Section 1 Open-Cut Excavating Work第一節 明り掘削の作業

Subsection 1 Time and Procedures of Excavating Work第一款 掘削の時期及び順序等

Article 355第三百五十五条

Investigation on the Workplace(作業箇所等の調査)
Article 355, paragraph (1)

In carrying out the excavating work of natural ground, when there is a risk of endangering workers due to collapse of natural ground, damage to underground-installed objects, etc., the employer must investigate in advance the workplace and natural ground surrounding the workplace regarding the following matters by boring or other appropriate methods, determine the time and procedures of excavation that conforms to what became known by the investigation, and carry out the work according to the procedures determined:

事業者は、地山の掘削の作業を行う場合において、地山の崩壊、埋設物等の損壊等により労働者に危険を及ぼすおそれのあるときは、あらかじめ、作業箇所及びその周辺の地山について次の事項をボーリングその他適当な方法により調査し、これらの事項について知り得たところに適応する掘削の時期及び順序を定めて、当該定めにより作業を行わなければならない。

Article 355, paragraph (1), item (i)

landform, nature of the soil and conditions of strata;

形状、地質及び地層の状態

Article 355, paragraph (1), item (ii)

existence and condition of cracks, water content, spring water and freezing;

き裂、含水、湧水及び凍結の有無及び状態

Article 355, paragraph (1), item (iii)

existence and condition of underground-installed objects, etc.; and

埋設物等の有無及び状態

Article 355, paragraph (1), item (iv)

existence and condition of high-temperature gas and vapor.

高温のガス及び蒸気の有無及び状態

Article 356第三百五十六条

Standard for Gradient of the Excavation Surface(掘削面のこう配の基準)
Article 356, paragraph (1)

When carrying out excavating work of natural ground (excluding natural ground composed of rock beds without cracks that cause collapse or fall of rocks, natural ground composed of sand, and natural ground in a condition which is liable to collapse due to blasting etc.; hereinafter the same applies in this Article) by the method of manual excavation (meaning the method of excavation without using excavating machines such as a power shovel and tractor shovel; hereinafter the same applies in the following Article), the employer must make the gradient of the excavation surface (in the case that there is a horizontal step with a depth of 2 m or more on the excavation surface, meaning each excavation surface divided by the horizontal step; the same applies hereinafter) the value equal to or less than that listed in the right column of the following Table in accordance with the type of the ground listed in the left column and the height of the excavation surface listed in the middle column of the same Table, respectively:

Type of the Natural GroundHeight of the Excavation Surface (Unit: m)Gradient of the Excavation Surface (Unit: Degrees)
natural ground composed of rock beds or hard clayLess than 590
5 or more75
other natural groundLess than 290
2 or more and less than 575
5 or more60

事業者は、手掘り(パワー・シヨベル、トラクター・シヨベル等の掘削機械を用いないで行なう掘削の方法をいう。以下次条において同じ。)により地山(崩壊又は岩石の落下の原因となるき裂がない岩盤からなる地山、砂からなる地山及び発破等により崩壊しやすい状態になつている地山を除く。以下この条において同じ。)の掘削の作業を行なうときは、掘削面(掘削面に奥行きが二メートル以上の水平な段があるときは、当該段により区切られるそれぞれの掘削面をいう。以下同じ。)のこう配を、次の表の上欄に掲げる地山の種類及び同表の中欄に掲げる掘削面の高さに応じ、それぞれ同表の下欄に掲げる値以下としなければならない。

地山の種類掘削面の高さ(単位 メートル)掘削面のこう配(単位 度)
岩盤又は堅い粘土からなる地山五未満九十
五以上七十五
その他の地山二未満九十
二以上五未満七十五
五以上六十
Article 356, paragraph (2)

In the case referred to in the preceding paragraph, when it is not possible to calculate the gradient because there are parts of the excavation surface that differ in slope from other parts, the slopes of the part of the excavation surface must be maintained so that the danger of collapse may not become greater than that prescribed in the same paragraph.

前項の場合において、掘削面に傾斜の異なる部分があるため、そのこう配が算定できないときは、当該掘削面について、同項の基準に従い、それよりも崩壊の危険が大きくないように当該各部分の傾斜を保持しなければならない。

Article 357第三百五十七条

Article 357, paragraph (1)

When carrying out the excavating work of natural ground composed of sand or of natural ground in a condition liable to collapse due to blasting, etc., by manual excavation, the employer must comply with requirements set forth in the following items:

事業者は、手掘りにより砂からなる地山又は発破等により崩壊しやすい状態になつている地山の掘削の作業を行なうときは、次に定めるところによらなければならない。

Article 357, paragraph (1), item (i)

for natural ground composed of sand, to make the gradient of the excavation surface 35 degrees or less, or make the height of the excavation surface less than 5 m; and

砂からなる地山にあつては、掘削面のこう配を三十五度以下とし、又は掘削面の高さを五メートル未満とすること。

Article 357, paragraph (1), item (ii)

for natural ground in a condition liable to collapse due to blasting, etc., to make the gradient of the excavation surface 45 degrees or less, or make the height of the excavation surface less than 2 m.

発破等により崩壊しやすい状態になつている地山にあつては、掘削面のこう配を四十五度以下とし、又は掘削面の高さを二メートル未満とすること。

Article 357, paragraph (2)

The provisions of paragraph (2) of the preceding Article apply mutatis mutandis to the case where it is not possible to calculate the gradient because parts of the excavation surface of the natural ground set forth in the preceding paragraph differ in slope from other parts.

前条第二項の規定は、前項の地山の掘削面に傾斜の異なる部分があるため、そのこう配が算定できない場合について、準用する。

Article 358第三百五十八条

Inspection(点検)
Article 358, paragraph (1)

When carrying out the work of open-cut excavation, the employer must take the following measures to prevent workers from dangers due to collapse of natural ground or fallen earth and rocks:

事業者は、明り掘削の作業を行なうときは、地山の崩壊又は土石の落下による労働者の危険を防止するため、次の措置を講じなければならない。

Article 358, paragraph (1), item (i)

to designate an inspector and have the inspector check the workplace and the natural ground surrounding the workplace before commencing the work for the day, after a heavy rain and a moderate or greater earthquake on the existence and condition of loose stones and cracks, and changes in water content, spring water and freezing conditions; and

点検者を指名して、作業箇所及びその周辺の地山について、その日の作業を開始する前、大雨の後及び中震以上の地震の後、浮石及びき裂の有無及び状態並びに含水、湧水及び凍結の状態の変化を点検させること。

Article 358, paragraph (1), item (ii)

to designate an inspector and have the inspector check for the existence and condition of loose stones and cracks, after blasting work, at places where the blasting work has been carried out and their surroundings.

点検者を指名して、発破を行なつた後、当該発破を行なつた箇所及びその周辺の浮石及びき裂の有無及び状態を点検させること。

Article 359第三百五十九条

Appointment of Operations Supervisor of Excavating Natural Ground(地山の掘削作業主任者の選任)
Article 359, paragraph (1)

As regards the work set forth in Article 6, item (ix) of the Order, the employer must appoint an operations supervisor of excavating natural ground from the persons who have completed the skill training course for operations supervisor of excavating natural ground and shoring.

事業者は、令第六条第九号の作業については、地山の掘削及び土止め支保工作業主任者技能講習を修了した者のうちから、地山の掘削作業主任者を選任しなければならない。

Article 360第三百六十条

Duties of the Operations Supervisor of Excavating Natural Ground(地山の掘削作業主任者の職務)
Article 360, paragraph (1)

The employer must have the operations supervisor of excavating natural ground carry out the following matters:

事業者は、地山の掘削作業主任者に、次の事項を行わせなければならない。

Article 360, paragraph (1), item (i)

to decide the work method and directly supervise the work;

作業の方法を決定し、作業を直接指揮すること。

Article 360, paragraph (1), item (ii)

to inspect the instruments and tools, and remove those defective; and

器具及び工具を点検し、不良品を取り除くこと。

Article 360, paragraph (1), item (iii)

to monitor the use of fall arrest equipment with the required performance, etc. and safety helmets.

要求性能墜落制止用器具等及び保護帽の使用状況を監視すること。

Article 361第三百六十一条

Prevention of Dangers Due to Collapse of Natural Ground(地山の崩壊等による危険の防止)
Article 361, paragraph (1)

When carrying out open-cut excavation work, if there is a risk of causing danger due to collapse of natural ground or falling of earth and rocks, the employer must, in advance, take measures to prevent the danger, such as setting up shoring, setting up protective nets and prohibiting persons engaged in work at the workshop from entering.

事業者は、明り掘削の作業を行う場合において、地山の崩壊又は土石の落下により危険を及ぼすおそれのあるときは、あらかじめ、土止め支保工を設け、防護網を張り、当該作業場において作業に従事する作業従事者の立入りを禁止する等当該危険を防止するための措置を講じなければならない。

Article 362第三百六十二条

Prevention of Dangers Due to Underground-Installed Objects(埋設物等による危険の防止)
Article 362, paragraph (1)

When carrying out open-cut excavation work at a place in the vicinity of underground installations, etc. or structures such as brick walls, concrete block walls and retaining walls, if there is a risk of endangering workers due to their damage, etc., the employer must not carry out the work unless measures to prevent the danger, such as reinforcing or relocating them, have been taken.

事業者は、埋設物等又はれんが壁、コンクリートブロツク塀、擁壁等の建設物に近接する箇所で明り掘削の作業を行なう場合において、これらの損壊等により労働者に危険を及ぼすおそれのあるときは、これらを補強し、移設する等当該危険を防止するための措置が講じられた後でなければ、作業を行なつてはならない。

Article 362, paragraph (2)

The measures set forth in the preceding paragraph, in the case where there is a risk of endangering workers due to damage to a gas conduit exposed by open-cut excavation work, must be measures such as protecting the gas conduit by suspension protection, support protection, etc., or relocating the gas conduit.

明り掘削の作業により露出したガス導管の損壊により労働者に危険を及ぼすおそれのある場合の前項の措置は、つり防護、受け防護等による当該ガス導管についての防護を行ない、又は当該ガス導管を移設する等の措置でなければならない。

Article 362, paragraph (3)

As regards the work for protecting gas conduits prescribed in the preceding paragraph, the employer must designate a person to supervise the work, and have the work carried out under the direct supervision by the person.

事業者は、前項のガス導管の防護の作業については、当該作業を指揮する者を指名して、その者の直接の指揮のもとに当該作業を行なわせなければならない。

Article 363第三百六十三条

Prohibition of Using Excavating Machines(掘削機械等の使用禁止)
Article 363, paragraph (1)

In carrying out the open-cut excavation work, when there is a risk of endangering workers due to damage to gas conduits, underground electric line or other underground structures by the use of excavating machine, loading and transporting machines, the employer must not use those machines.

事業者は、明り掘削の作業を行なう場合において、掘削機械、積込機械及び運搬機械の使用によるガス導管、地中電線路その他地下に存する工作物の損壊により労働者に危険を及ぼすおそれのあるときは、これらの機械を使用してはならない。

Article 364第三百六十四条

Traveling Route of Transporting Machines(運搬機械等の運行の経路等)
Article 364, paragraph (1)

When carrying out the open-cut excavation work, the employer must determine in advance the traveling route for the transporting machine, excavating machine and loading machine (excluding a vehicle type construction equipment and a vehicle type material handling machine, etc.; hereinafter referred to as "transporting machine, etc." in this Chapter), and the method for entering and leaving the place for those machines to load and unload the earth and rocks, and make them known to the workers concerned.

事業者は、明り掘削の作業を行うときは、あらかじめ、運搬機械、掘削機械及び積込機械(車両系建設機械及び車両系荷役運搬機械等を除く。以下この章において「運搬機械等」という。)の運行の経路並びにこれらの機械の土石の積卸し場所への出入の方法を定めて、これを関係労働者に周知させなければならない。

Article 365第三百六十五条

Arrangement of a Guide(誘導者の配置)
Article 365, paragraph (1)

When carrying out open-cut excavation work, if a transporting machine, etc. approaches the work location by going backwards or there is a risk of its falling, the employer must place a guide and have that person guide these machines.

事業者は、明り掘削の作業を行う場合において、運搬機械等が、当該作業箇所に後進して接近するとき、又は転落するおそれのあるときは、誘導者を配置し、その者にこれらの機械を誘導させなければならない。

Article 365, paragraph (2)

The operator of the transporting machine, etc., set forth in the preceding paragraph must follow the instruction given by the guide set forth in the same paragraph.

前項の運搬機械等の運転者は、同項の誘導者が行う誘導に従わなければならない。

Article 366第三百六十六条

Wearing Safety Helmets(保護帽の着用)
Article 366, paragraph (1)

When carrying out the work of open-cut excavation, the employer must have the worker engaging in the work wear a safety helmet in order to prevent workers from dangers due to objects that come flying or falling.

事業者は、明り掘削の作業を行なうときは、物体の飛来又は落下による労働者の危険を防止するため、当該作業に従事する労働者に保護帽を着用させなければならない。

Article 366, paragraph (2)

The worker engaging in the work set forth in the preceding paragraph must wear the safety helmet set forth in the same paragraph.

前項の作業に従事する労働者は、同項の保護帽を着用しなければならない。

Article 367第三百六十七条

Maintenance of Illumination(照度の保持)
Article 367, paragraph (1)

As regards the place where the work of an open-cut excavation is carried out, the employer must maintain necessary illumination for safely carrying out the work.

事業者は、明り掘削の作業を行なう場所については、当該作業を安全に行なうため必要な照度を保持しなければならない。

Subsection 2 Shoring第二款 土止め支保工

Article 368第三百六十八条

Material(材料)
Article 368, paragraph (1)

As regards materials of shoring, the employer must not use those having marked damage, deformation or corrosion.

事業者は、土止め支保工の材料については、著しい損傷、変形又は腐食があるものを使用してはならない。

Article 369第三百六十九条

Structure(構造)
Article 369, paragraph (1)

The employer must make the structure of the shoring solid in accordance with the condition of landform, nature of the soil, strata, cracks, water content, spring water, freezing and underground-installed objects, etc., pertaining to the natural ground where the shoring is to be installed.

事業者は、土止め支保工の構造については、当該土止め支保工を設ける箇所の地山に係る形状、地質、地層、き裂、含水、湧水、凍結及び埋設物等の状態に応じた堅固なものとしなければならない。

Article 370第三百七十条

Assembly Drawing(組立図)
Article 370, paragraph (1)

When assembling the shoring, the employer must prepare an assembly drawing in advance, and assemble the shoring according to the drawing.

事業者は、土止め支保工を組み立てるときは、あらかじめ、組立図を作成し、かつ、当該組立図により組み立てなければならない。

Article 370, paragraph (2)

The assembly drawing set forth in the preceding paragraph must indicate the arrangement, size and materials of components such as sheet piles, piles, shore laggings, wales, struts, and the time and procedures of installation.

前項の組立図は、矢板、くい、背板、腹おこし、切りばり等の部材の配置、寸法及び材質並びに取付けの時期及び順序が示されているものでなければならない。

Article 371第三百七十一条

Installation of Components(部材の取付け等)
Article 371, paragraph (1)

As regards installation, etc. of the components of the shoring, the employer must comply with the requirements set forth in the following items:

事業者は、土止め支保工の部材の取付け等については、次に定めるところによらなければならない。

Article 371, paragraph (1), item (i)

to firmly mount the wales and struts on sheet piles, piles, etc., to prevent them from coming off;

切りばり及び腹おこしは、脱落を防止するため、矢板、くい等に確実に取り付けること。

Article 371, paragraph (1), item (ii)

to use butt joints for joints of compression components (excluding angle braces);

圧縮材(火打ちを除く。)の継手は、突合せ継手とすること。

Article 371, paragraph (1), item (iii)

to firmly fasten the connecting parts of struts or angle braces and the crossing parts of struts with doubling plates and bolts, or connect them by welding or other methods to make them solid;

切りばり又は火打ちの接続部及び切りばりと切りばりとの交さ部は、当て板をあててボルトにより緊結し、溶接により接合する等の方法により堅固なものとすること。

Article 371, paragraph (1), item (iv)

for shoring with a middle support pole, to firmly mount struts on the middle support pole; and

中間支持柱を備えた土止め支保工にあつては、切りばりを当該中間支持柱に確実に取り付けること。

Article 371, paragraph (1), item (v)

when struts are supported by things other than the components such as the columns of a building, to make the supports strong enough to bear the load applied.

切りばりを建築物の柱等部材以外の物により支持する場合にあつては、当該支持物は、これにかかる荷重に耐えうるものとすること。

Article 372第三百七十二条

Work of Installing or Removing Struts(切りばり等の作業)
Article 372, paragraph (1)

When carrying out the work set forth in Article 6, item (x) of the Order, the employer must take the following measures:

事業者は、令第六条第十号の作業を行うときは、次の措置を講じなければならない。

Article 372, paragraph (1), item (i)

to prohibit persons other than persons engaged in work concerned from entering the place where the work is carried out, by indicating the prohibition in a conspicuous place or by other methods;

当該作業を行う箇所に関係する作業従事者以外の者が立ち入ることについて、禁止する旨を見やすい箇所に表示することその他の方法により禁止すること。

Article 372, paragraph (1), item (ii)

when raising or lowering materials, instruments or tools, to have workers use lifting ropes, lifting bags, etc.

材料、器具又は工具を上げ、又は下ろすときは、つり綱、つり袋等を労働者に使用させること。

Article 373第三百七十三条

Inspection(点検)
Article 373, paragraph (1)

When having installed shoring, the employer must inspect the following matters once every period not exceeding seven days, after a moderate or greater earthquake, and after the occurrence of a situation that has a risk of rapidly weakening the ground due to heavy rain, etc., and immediately reinforce or make repairs when having found any abnormality:

事業者は、土止め支保工を設けたときは、その後七日をこえない期間ごと、中震以上の地震の後及び大雨等により地山が急激に軟弱化するおそれのある事態が生じた後に、次の事項について点検し、異常を認めたときは、直ちに、補強し、又は補修しなければならない。

Article 373, paragraph (1), item (i)

existence and condition of damage, deformation, corrosion, displacement and coming off of components;

部材の損傷、変形、腐食、変位及び脱落の有無及び状態

Article 373, paragraph (1), item (ii)

degree of compression of struts; and

切りばりの緊圧の度合

Article 373, paragraph (1), item (iii)

condition of the connecting parts, mounting parts and crossing parts of components.

部材の接続部、取付け部及び交さ部の状態

Article 374第三百七十四条

Appointment of Operations Supervisor of Shoring(土止め支保工作業主任者の選任)
Article 374, paragraph (1)

As regards the work set forth in Article 6, item (x) of the Order, the employer must appoint an operations supervisor of shoring from the persons who have completed the skill training courses for operations supervisor of excavating natural ground and shoring.

事業者は、令第六条第十号の作業については、地山の掘削及び土止め支保工作業主任者技能講習を修了した者のうちから、土止め支保工作業主任者を選任しなければならない。

Article 375第三百七十五条

Duties of the Operations Supervisor of Shoring(土止め支保工作業主任者の職務)
Article 375, paragraph (1)

The employer must have the operations supervisor of shoring carry out the following matters:

事業者は、土止め支保工作業主任者に、次の事項を行わせなければならない。

Article 375, paragraph (1), item (i)

to decide the work method and directly supervise the work;

作業の方法を決定し、作業を直接指揮すること。

Article 375, paragraph (1), item (ii)

to check for defects in material and inspect instruments and tools, and remove those defective; and

材料の欠点の有無並びに器具及び工具を点検し、不良品を取り除くこと。

Article 375, paragraph (1), item (iii)

to monitor the use of fall arrest equipment with the required performance, etc. and safety helmets.

要求性能墜落制止用器具等及び保護帽の使用状況を監視すること。

© 2026 japanlaw.orgA copy for reading and reference — not an official source, and not legal advice. Only the Japanese text published by the government has legal effect.Run by Genjido LLC (源氏道合同会社) · contact@genjido.comContactSourcesTermsPrivacy