Chapter XII Prevention of Dangers Due to Debris Flow
The law as Ministerial Order Partially Amending the Ordinance on Industrial Safety and Health (Ministry of Health, Labour and Welfare Order No. 12 of 2025) leaves it, with the words it changes marked.
The main text is read a page at a time: a chapter to a page, and a long chapter in runs of articles. The whole main text, and the supplementary provisions and appended tables this amendment changes. Those it leaves untouched are on the page for the text in force.
Chapter XII Prevention of Dangers Due to Debris Flow第十二章 土石流による危険の防止
Article 575-9第五百七十五条の九
Investigation and Record(調査及び記録)
Article 575-9, paragraph (1)
In carrying out construction work (excluding temporary work; the same applies hereinafter) on a river where there is a risk of debris flow incidental to rain, melting snow or earthquake (hereinafter referred to as "river with a danger of debris flow"), the employer must investigate in advance the condition of upper reaches of the river from the workplace and the surrounding area in order to prevent workers from dangers due to debris flow, and record the result of the investigation.
Rules Concerning Prevention of Industrial Accidents Due to Debris Flows(土石流による労働災害の防止に関する規程)
Article 575-10, paragraph (1)
When carrying out construction work on the river with a danger of debris flows, the employer must establish in advance rules concerning the prevention of industrial accidents due to debris flows.
The rules set forth in the preceding paragraph must indicate the following matters:
前項の規程は、次の事項が示されているものでなければならない。
Article 575-10, paragraph (2), item (i)
the method of ascertaining the amount of rainfall;
降雨量の把握の方法
Article 575-10, paragraph (2), item (ii)
the measures to be taken in the case rainfall, melting snow or an earthquake have taken place;
降雨又は融雪があつた場合及び地震が発生した場合に講ずる措置
Article 575-10, paragraph (2), item (iii)
the measures to be taken in the case phenomena that precedes a debris flow have been noted;
土石流の発生の前兆となる現象を把握した場合に講ずる措置
Article 575-10, paragraph (2), item (iv)
the warning and the method of evacuation in the case a debris flow occurs; and
土石流が発生した場合の警報及び避難の方法
Article 575-10, paragraph (2), item (v)
details and timing of evacuation drills.
避難の訓練の内容及び時期
Article 575-10, paragraph (3)
The employer must make the rules set forth in paragraph (1) suitable to what became known by the investigation pursuant to the provisions of the preceding Article.
When carrying out construction work on the river with a danger of debris flows, the employer must ascertain the amount of rainfall during the preceding 24 hours before commencing work and the amount of rainfall for each hour after having commenced work using a rain gauge or other method and keep their record.
In carrying out construction work on a river with a danger of debris flow where there is a risk of a debris flow due to rainfall, the employer must take measures to become aware of the occurrence of a debris flow at an early stage, such as placing a watcher; provided, however, that this does not apply when the work has been promptly suspended and persons engaged in work have been evacuated to a safe place.
In carrying out construction work on a river with a danger of debris flow where there is an imminent danger of an industrial accident due to a debris flow, the employer must immediately suspend the work and evacuate the persons engaged in work to a safe place.
In carrying out construction work on a river with a danger of debris flow, the employer must provide warning equipment such as a siren and an emergency bell, etc., to promptly inform the persons engaged in work relating to that work that a debris flow has occurred, and make the location of the equipment known to the persons engaged in work concerned.
The employer must maintain the warning equipment set forth in the preceding paragraph to properly function at all times.
事業者は、前項の警報用の設備については、常時、有効に作動するように保持しておかなければならない。
Article 575-15第五百七十五条の十五
Evacuation Equipment(避難用の設備)
Article 575-15, paragraph (1)
In carrying out construction work on a river with a danger of debris flow, the employer must provide equipment for evacuation such as ascending piers, ladders, etc., at appropriate places for the safe evacuation of persons engaged in work when a debris flow occurs, and make the location of the equipment and its using method known to the persons engaged in work concerned.
The employer must maintain the evacuation equipment set forth in the preceding paragraph to properly function at all times.
事業者は、前項の避難用の設備については、常時有効に保持しなければならない。
Article 575-16第五百七十五条の十六
Evacuation Drills(避難の訓練)
Article 575-16, paragraph (1)
In carrying out construction work on a river with a danger of debris flow, in order to prepare for the occurrence of a debris flow, the employer must conduct an evacuation drill for the persons engaged in work concerned once without delay after the commencement of the work, and thereafter once every period not exceeding six months.
When having conducted the evacuation drill, the employer must record the following matters and preserve the records for three years:
事業者は、避難の訓練を行つたときは、次の事項を記録し、これを三年間保存しなければならない。
Article 575-16, paragraph (2), item (i)
the date of the training;
実施年月日
Article 575-16, paragraph (2), item (ii)
the name of the persons who have undergone the training; and
訓練を受けた者の氏名
Article 575-16, paragraph (2), item (iii)
the details of the training.
訓練の内容
Copy link
Coming into force施行
The day a law or an amendment starts to apply. It is often months or years after promulgation, so that people have time to prepare. The Ministry of Justice's English usually says a law "comes into force" or "comes into effect", and sometimes calls the day its "enforcement date". Its "enforcement" more often means the word's other sense, carrying a law out, as in an Order for Enforcement (施行令), the Cabinet Order (政令) that sets out the details for carrying out an Act.