Article 327Statutory Liens for Construction Work for Immovables

第三百二十七条(不動産工事の先取特権)

Statutory lien for construction work for immovables exists, with respect to immovables, in connection with the expenses of construction work performed by a person that designs, constructs or supervises construction regarding the immovables of the obligor.

不動産の工事の先取特権は、工事の設計、施工又は監理をする者が債務者の不動産に関してした工事の費用に関し、その不動産について存在する。

The statutory liens referred to in the preceding paragraph exist with respect to the relevant increased value alone, but only if there is a current increase in the value of the immovables resulting from the construction work.

前項の先取特権は、工事によって生じた不動産の価格の増加が現存する場合に限り、その増価額についてのみ存在する。