- Law: 労働安全衛生規則 (Ordinance on Industrial Safety and Health), 昭和四十七年労働省令第三十二号
- English title "Ordinance on Industrial Safety and Health": Ministry of Justice translation
- Kind: MinisterialOrdinance — the distinction between 法律 (Act), 政令 (Cabinet Order), 省令 (Ministerial Order) and 条例 (local ordinance) decides who may issue it and what it may say.
- Provision: 第三百八十三条 (Article 383)（施工計画の変更） — address `art-383`
- Text in force since: 2026-10-01
- URL (the page that opens at this provision): https://japanlaw.org/ja/industrial-safety-and-health-ordinance/art-383
- e-Gov law ID: 347M50002000032 — never renamed. A permanent link, `/l/{lawId}/{address}` on this site, redirects to the page.
- Every provision below carries its address and its URL on the line under it.
- Japanese text: e-Gov 法令検索, Digital Agency (デジタル庁). English: as marked on each line below.

Only the Japanese as published by the government has legal effect; the text
below is a copy of it. Every English rendering below is a translation and
says which kind: the Ministry of Justice's translation, or this
site's machine translation, whose model and date the Sources list names.
They are never merged and never substituted for one another.

---

### 第三百八十三条（施工計画の変更） — (Alteration in Construction Plan)
<sup>caption: Ministry of Justice translation — Japanese Law Translation Database System</sup>
<sup>art-383 · https://japanlaw.org/ja/industrial-safety-and-health-ordinance/art-383</sup>

      **第一項**  事業者は、ずい道等の掘削の作業を行う場合において、第三百八十条第一項の施工計画が第三百八十一条第一項の規定による観察、第三百八十二条の規定による点検、第三百八十二条の二の規定による測定等により知り得た地山の状態に適応しなくなつたときは、遅滞なく、当該施工計画を当該地山の状態に適応するよう変更し、かつ、変更した施工計画によつて作業を行わなければならない。
      <sup>art-383/par-1 · https://japanlaw.org/ja/industrial-safety-and-health-ordinance/art-383/par-1</sup>
      In carrying out excavating work of tunnels, etc., when the construction plan set forth in Article 380, paragraph (1) becomes unsuitable to the conditions of natural ground which became known by the observation pursuant to the provisions of Article 381, paragraph (1), the inspection pursuant to the provisions of Article 382, the measurement pursuant to the provisions of Article 382-2, etc., the employer must change the construction plan without delay so that suits the conditions of the natural ground, and carry out the excavating work according to the changed construction plan.
      <sup>Ministry of Justice translation — Japanese Law Translation Database System</sup>

---

## Cites
- art-383/par-1: 第三百八十条第一項 → 労働安全衛生規則 第三百八十条第一項 (Article 380, paragraph (1)), art-380/par-1 — https://japanlaw.org/ja/industrial-safety-and-health-ordinance/art-380/par-1
- art-383/par-1: 第三百八十一条第一項 → 労働安全衛生規則 第三百八十一条第一項 (Article 381, paragraph (1)), art-381/par-1 — https://japanlaw.org/ja/industrial-safety-and-health-ordinance/art-381/par-1
- art-383/par-1: 第三百八十二条 → 労働安全衛生規則 第三百八十二条 (Article 382), art-382 — https://japanlaw.org/ja/industrial-safety-and-health-ordinance/art-382
- art-383/par-1: 第三百八十二条の二 → 労働安全衛生規則 第三百八十二条の二 (Article 382-2), art-382-2 — https://japanlaw.org/ja/industrial-safety-and-health-ordinance/art-382-2

---

## Sources

- e-Gov 法令検索, Digital Agency (デジタル庁) — 労働安全衛生規則 — the text in force from 2026-10-01 (https://laws.e-gov.go.jp/law/347M50002000032/20261001_508M60000100116), retrieved 2026-11-13