# 労働安全衛生規則 / Ordinance on Industrial Safety and Health — 第百五十一条の百二十二 (Article 151-122)

This is the Markdown twin of https://japanlaw.org/en/industrial-safety-and-health-ordinance/art-151-122. Every law, and how to address a provision: https://japanlaw.org/llms.txt. The same laws as MCP tools (no sign-in): https://japanlaw.org/mcp.

- Law: 労働安全衛生規則 (Ordinance on Industrial Safety and Health), 昭和四十七年労働省令第三十二号
- English title "Ordinance on Industrial Safety and Health": Ministry of Justice translation
- Kind: MinisterialOrdinance — the distinction between 法律 (Act), 政令 (Cabinet Order), 省令 (Ministerial Order) and 条例 (local ordinance) decides who may issue it and what it may say.
- Provision: 第百五十一条の百二十二 (Article 151-122)（スリングの点検） — address `art-151-122`
- Text in force since: 2026-10-01
- URL (the page that opens at this provision): https://japanlaw.org/en/industrial-safety-and-health-ordinance/art-151-122
- e-Gov law ID: 347M50002000032 — never renamed. A permanent link, `/l/{lawId}/{address}` on this site, redirects to the page.
- Every provision below carries its address and its URL on the line under it.
- Japanese text: e-Gov 法令検索, Digital Agency (デジタル庁). English: as marked on each line below.

Only the Japanese as published by the government has legal effect; the text
below is a copy of it. Every English rendering below is a translation and
says which kind: the Ministry of Justice's translation, or this
site's machine translation, whose model and date the Sources list names.
They are never merged and never substituted for one another.

---

### 第百五十一条の百二十二（スリングの点検） — Inspection of Slings
<sup>caption: machine translation, not official</sup>
<sup>art-151-122 · https://japanlaw.org/en/industrial-safety-and-health-ordinance/art-151-122</sup>

      **第一項**  事業者は、架線集材機械を用いて作業を行うときは、その日の作業を開始する前に、当該作業に用いるスリングの状態について点検し、異常を認めたときは、直ちに、補修し、又は取り替えなければならない。
      <sup>art-151-122/par-1 · https://japanlaw.org/en/industrial-safety-and-health-ordinance/art-151-122/par-1</sup>
      When carrying out work using a cable yarding machine, the employer must, before starting the work of the day, check the condition of the slings used for the work, and if an abnormality is found, must immediately repair or replace them.
      <sup>machine translation, not official</sup>

---

## Sources

- e-Gov 法令検索, Digital Agency (デジタル庁) — 労働安全衛生規則 — the text in force from 2026-10-01 (https://laws.e-gov.go.jp/law/347M50002000032/20261001_508M60000100116), retrieved 2026-11-13
- Japanese Law Translation Database System, Ministry of Justice (法務省) — Ordinance on Industrial Safety and Health — Ministry of Justice translation (https://www.japaneselawtranslation.go.jp/en/laws/view/3878/tb), retrieved 2026-11-13
- claude-sonnet-5-5 — Machine translation, batch industrial-safety-and-health-ordinance-20261113T030819-028, translated 2026-11-13
- This site's parser, version 240 — 労働安全衛生規則 — structure, counts, cross-references and defined terms, computed 2026-11-13